MAKING PROGRESS: DOWNTOWN TUSCALOOSA CONSTRUCTION UPDATE

Sewer Spill00000000

road work

The Alabama Department of Transportation and city of Tuscaloosa are making slow but steady progress on their Lurleen B. Wallace Boulevard project.

Construction, which began last summer, won’t be ending until early 2020.

But University Boulevard between southbound and northbound Lurleen B. Wallace Boulevard is now open again.

But other streets are still blocked off, including:

 Southbound

  • Sixth Street will remain closed on the west side until late August
  • Seventh Street will remain closed on the west side until late August
  • Eighth Street will remain closed on the west side until early October

Northbound

  • Sixth Street will remain closed on the west side until early October
  • Paul Bryant Drive will remain closed on the west until early October
  • 11th Street will remain closed on the west side until late September
  • 25th Avenue will remain closed north of 14th Street until the end of the project
  • View ALDOT’s map of what’s open and closed below.